Construction and preparation of precast concrete foundations for spherical tank foundations and construction of spherical tank foundations for the CPF within the Halfaya Oil Field (GPP)– Maysan.
May 31, 2024
Construction of Sulfur Storage Units 1 & 2 and Guard Room No. (3) in the Halfaya Oil Field – Maysan.
May 31, 2024Commencement Date/ 2020
Project: the construction of a pipeline network for transporting natural gas and crude oil in the Halfaya Oil Field – Maysan.
Commencement Date/ 2020
Project Overview/ The work involves laying and welding 6 pipelines (4، 8، 10، 12، two lines of 24 inch pipes) covering a total of 60 km from GPP to CPF1:
1- 10” C5+ Condensate Interconnection Trunkline from GPP to HPS.
2- 4″ HP Fuel Gas Interconnection Trunkline from GPP to CPF1.
3- 24″ Dry Gas Interconnection Trunkline from GPP to Amarah &Kahala Power Plant.
4- 24″ Raw Gas Interconnection Trunkline from CPF3 to GPP.
5- 8″ Condensate Interconnection Trunkline from CPF1&CPF3 to GPP.
6- 12″ LP Fuel Gas Interconnection Trunkline from GPP to CPF1&CPF3
including Material inspection، Unloading and Handling، Right of way survey، Grading، Stringing، Trenching، Line-up، Welding، NDT، Anti-corrosion Coating، Peeling test، Holiday test، Tie-in، Lowering In، Backfilling، Pigging، Hydrostatic testing، Road crossing، River crossing، Cathodic protection، Clean Up، Restoration، HDD operations، heat treatment، cathodic protection، and all necessary requirements for project completion.
Project Cost: $7،860،505.00 USD. The project was successfully completed in 2023.