the construction of a pipeline network for transporting natural gas and crude oil in the Halfaya Oil Field – Maysan.
May 31, 2024
Construction of roads in GPP and LPG area in CPF2
May 31, 2024Overview of the Project/ The work includes the construction and furnishing of two steel structure sulfur storage، equipped with a fire extinguishing system and storage facilities. Additionally، the project involves constructing and furnishing Guard Room No. (3) according to the agreed-upon technical specifications.
Project Cost: $684،145.17 USD. The project was successfully completed in 2023.