Construction of an asphalt road of CPF3 within the Halfaya Oil Field – Maysan.
May 31, 2024
the construction of a pipeline network for transporting natural gas and crude oil in the Halfaya Oil Field – Maysan.
May 31, 2024Commencement Date/ 2020
Project Overview/ The work includes pouring and preparing 650 precast Piles (30*30CM)with a total length of 19 meter for the foundations of eleven spherical tanks in Halfaya GPP، and constructing the spherical eleven tanks foundation، installing anchor bolts for the tanks steel structures، and providing moisture and corrosion protection، and conducting all necessary inspections to ensure work quality.
Project Cost: $15،897،890.00 USD. The project was successfully completed in 2021.