Infrastructure Construction in Um Qasr District
May 31, 2024
Construction of Walls for the (CPF) Area in the Halfaya Oil Field، Maysan Governorate
May 31, 2024The projects include all road paving and landscaping works for the West Qurna 2 field، in addition to road paving and infrastructure works for internal and external roads in region (A) within the field. It involves the construction of a fully-equipped residential and administrative camp with all services، wireless communication units، and external gates. Our company collaborated with Noor Baghdad Contracting Limited during the period of this project. Additionally، there are maintenance and rehabilitation contracts for the roads in West Qurna 2 field، covering all road and yards maintenance tasks، installation of traffic signs، road planning، construction of box and pipe culverts، reconstruction of field roads with the installation of T-walls، work required for concrete protection with HDPE layers، cleaning of sludge pits، and a contract for the design and implementation of custom Zone-B dedicated to storing equipment for LukOil company، including electrical and IT works، safety requirements، conducting bore hole testing، and the construction of shades، parking areas and workshops، including concrete floor casting and site planning.
Contract No.1
Commencement Date: 2011
Project Delivery: 2013
Project Budget: $18،000،000 USD

Contract No. 2
Commencement Date: 2014
Project Delivery: 2016
Project Budget: $49،000،000 USD


Contract No. 3
Commencement Date: 2017
Project Delivery: 2021
Project Budget: $7،000،000 USD





Contract No. 4
Commencement Date: 2018
Project Delivery: 2022
Project Budget: $19،795،000 USD