Supply، transport، and installation of concrete slabs and observation towers for Zone S1 & S2 in the East Baghdad Field.
May 31, 2024
Bismaya New City Project for the construction of sewage and rainwater pipelines.
May 31, 2024Commencement Date: 2019
Project Overview: Preparing and installing 16-inch diameter pipeline for the transportation of crude oil in East Baghdad Oil Field. Providing the necessary machinery، teams، and equipment for Norinco، (Chinese company)، in collaboration with Noor Baghdad General Contracting Company for the completion of the Provision of EPCC Service for Pipeline Corridor from FPF to CPF Project. Material inspection، Unloading and Handling، Right of way survey، Grading، Stringing، Trenching، Line-up، Welding، NDT، Anti-corrosion Coating،Peeling test، Holiday test، Tie-in، Lowering In، Backfilling، Pigging، Hydrostatic testing، Road crossing ، River crossing، Cathodic protection، Clean Up and Restoration.
Project Budget: $1،000،000 USD
Project Delivery: 2020