Construction of an asphalt road of CPF3 within the Halfaya Oil Field – Maysan.
May 31, 2024Our Work with China Petroleum Engineering and Construction Corporation
Commencement Date: 2017
Brief Overview: The work included excavating over 3،000 m³ to build a brick wall with a height exceeding 3 meters. Installing (B.R.C) fences with barbed wire، in addition to the installation of hydraulic steel gates. The total length of the wall reached 5 km. The project was executed in partnership with Noor Baghdad General Contracting Company، serving China Petroleum Engineering & Construction Corporation (CPECC).
Project Budget: $1،250،000 USD
Project Delivery: 2018